Structure and efficient linking 1

Status
Not open for further replies.

WhiteyWhitey

Electrical
Feb 3, 2009
61
Hi There,

I am working on quite a large project with a 600 line proramme.

We have had several restructures of the programme and every time the programme shifts, I have to move a repeated unit of work (a section of cabling) and re do all of the links between each work section. Takes ages and it feels inefficient.

Is there a better way to do this?

For example

I have a task CABLE INSTALLATION
with subtasks

EXCAVATE
SET UP CABLE DRUM
INSTALL BACK FILL

every time I rearrange the order of the sections I need to re do manually the links between the Back fill and jointing, the excavation and the next section excavation. etc.

Hope thats a clear explanation of the problem.

Thanks in advance.
 
Replies continue below

Recommended for you

Hi WhiteyWhitey,

It sounds like there is a constraint set on Back fill and/or jointing.

Look in the indicator column in the task sheet or click on the task and go to the 'Advanced' tab. Set the task to start 'as soon as possible'.

I have written an article on constraints which you might find useful.
Kind regards
ProjectMonkey

T morphy
 
"Hope thats a clear explanation of the problem"

Not really. If you have the correct linking, everything should move to right ot left as expected. Can you post an example sheet?

TTFN

FAQ731-376
 