Hi There,
I am working on quite a large project with a 600 line proramme.
We have had several restructures of the programme and every time the programme shifts, I have to move a repeated unit of work (a section of cabling) and re do all of the links between each work section. Takes ages and it feels inefficient.
Is there a better way to do this?
For example
I have a task CABLE INSTALLATION
with subtasks
EXCAVATE
SET UP CABLE DRUM
INSTALL BACK FILL
every time I rearrange the order of the sections I need to re do manually the links between the Back fill and jointing, the excavation and the next section excavation. etc.
Hope thats a clear explanation of the problem.
Thanks in advance.
I am working on quite a large project with a 600 line proramme.
We have had several restructures of the programme and every time the programme shifts, I have to move a repeated unit of work (a section of cabling) and re do all of the links between each work section. Takes ages and it feels inefficient.
Is there a better way to do this?
For example
I have a task CABLE INSTALLATION
with subtasks
EXCAVATE
SET UP CABLE DRUM
INSTALL BACK FILL
every time I rearrange the order of the sections I need to re do manually the links between the Back fill and jointing, the excavation and the next section excavation. etc.
Hope thats a clear explanation of the problem.
Thanks in advance.