- May 6, 2003
- 32
I am planning some maintenance work on a 34% aq NH3 line.
Before we carry out the work, we plan to flush the lines out with water.
Is there a recommended flush requirement (quantatiy or velocity) dependent on id and length of pipe?
I also have a centrifugal pump in the line and am not entirely sure how this will restrict the flow through the line.
Thanks