Hello,
Good afternoon, we are using MS Project to track hours of a project that has already been completed.
I am entering the hours in the Resource Usage View.
However, every now and then if I entered:
Monday 6 hours
Tuesday 2 hours
It automatically chages to:
Monday 6.37 hours
Tuesday 1.63 hours
Note that the total hours do not change, but we are not looking to "optimize" a project that has already been completed. We just want to log all the hours.
Is there a way to turn this automatic calculation OFF?
Thanking you in advance,
Joseph