Entered hours in Resource Usage change automatically

Status
Not open for further replies.

josephv

Mechanical
Oct 1, 2002
683

Hello,

Good afternoon, we are using MS Project to track hours of a project that has already been completed.

I am entering the hours in the Resource Usage View.

However, every now and then if I entered:

Monday 6 hours
Tuesday 2 hours

It automatically chages to:

Monday 6.37 hours
Tuesday 1.63 hours

Note that the total hours do not change, but we are not looking to "optimize" a project that has already been completed. We just want to log all the hours.

Is there a way to turn this automatic calculation OFF?

Thanking you in advance,

Joseph
 
Replies continue below

Recommended for you

Ok... I think I know what I am doing wrong.

For this case we should use "Actual Work"
 