lahpe65
Structural
- Jan 3, 2003
- 46
I am involved in a project where we are backfilling against an existing below grade wall. There is a street adjacent to this wall that must be maintained. This wall has been in place for 50+ years. I have been told to add weep holes to the existing wall prior to backfilling against it. I am hesitant to agree to this. There have been no drainage issues and I am afraid that by adding these weepholes we would be changing the make-up of the soil on the street side of the existing wall. Possibly causing additional settlement/movement on the wall as the structure above is demolished. Any thoughts?