I am a Project Manager for a Steel Fabricator. Often, there is much incomplete information on design drawings which necessitate field verification, prior to development of shop drawings.
Is the General Contractor responsible to furnish this needed information to the E.O.R. to add to the design drawings or is it the responsibility of the steel fabricator to go to the site, and field measure everything to add to the first set of shop drawings? What saith the AISD? 9th please?