I'm interested in any comments you may have as to the interpretation of this paragraph.
Some folks I've talked with, say that in the case of a small pipe vessel where seamless pipe is used and both head seams total < 50 ft and were welded by the same welder, one spot is sufficient. I'm having difficulty in reconciling that practice with UW 52(4).