At what point is a unfired pressure vessel considered a miniature and fall under UM code requirements
 
Replies continue below

Recommended for you

See paragraph U-1(j)

Depends on design pressure and internal volume. Note that a UM stamp is an option (subject to customer / local jurisdiction approval; you can always stamp U.