ART007
Electrical
- Dec 30, 2012
- 4
We are using an automatic closing system in 132/33kV substation, where we have 4 nos. of 132/33kV transformers which runs in 2 groups. T1||T2 and T3||T4.
Scheme is such that if one transformer trips, the left alone transformer from that group get paralleled with the other healthy group of transformers which are running in parallel by closing Sections / coupler as appropriate.
My question is that what will be the significance transformers' tap position. In our system, the tap difference of 4 taps is allowed and transformer can be paralleled. However, what will be the impact on Sections closing which have synchrocheck closing of CBs.
Also, will there be any special consideration when we talk about the sharing of load?
Thanks for your time and feed backs.
ART
Scheme is such that if one transformer trips, the left alone transformer from that group get paralleled with the other healthy group of transformers which are running in parallel by closing Sections / coupler as appropriate.
My question is that what will be the significance transformers' tap position. In our system, the tap difference of 4 taps is allowed and transformer can be paralleled. However, what will be the impact on Sections closing which have synchrocheck closing of CBs.
Also, will there be any special consideration when we talk about the sharing of load?
Thanks for your time and feed backs.
ART