CKent
Electrical
- Aug 27, 2003
- 42
I am a T&D planning engineer for an electric utility.
I am doing bench marking/ cross referencing involving different utility practice for planning distribution facilities.
From my previous experience, our subtransmission system (115 kV) is looped while our distribution system (34.5 kV or 13.8 kV) is radial with N.O. connection from other source for load shifting in case of troubles. Back there, one of our basic criteria is to plan for expansion when the distribution line reaches approx. 70% loading. Expansion could either be by upgrading the involve feeder or expansion from another source which can unload the affected feeder through load shifting. We evaluate base on actual peak loading and not based on applied connected loads being serve by the feeders.
Currently, I am working for an electric utility away from my country but which is having different system and somehow different philosophy. Here, we have a system which is independent having our own generation and T&D system. We have inter-tie with a larger network/system @ 380kV. However, from 115 kV system dowstream, all are radial but with redundancy. Community areas are serve by 13.8 kV loop (2-feeders with N.O. connection in between for redundancy). For connecting new or additional loads, I would evaluate the feeder based on actual historical peak load of the loop to check if capacity is still available for the new connection. Of course with due consideration of the possible future load increase based on the connected load. Ideally, I would recommend favorably if peak load has not reached 80%-85% and the potential for increase is still there due to the connected transformer capacities.
However, operations people will always argue and sometimes reject recommendation saying that the same feeder is over committed considering the connected load (despite peak loading way below the capacity of the single feeder). I know that their consideration is mostly on technical side and somehow not considering the economic side of this philosophy.
We are planning to propose to adapt an official philosophy which considers the peak load as a means to evaluate utilization of facilities (not only feeders but also dist. XF).
In this regard, I am bench marking to gather prevailing philosophy on this issue. We would appreciate if somebody can inform of their followed philosophy in their utility planning or if there are other utility company following the committed load/connected load instead of the peak load in their planning criteria?
Thanks!
CK
I am doing bench marking/ cross referencing involving different utility practice for planning distribution facilities.
From my previous experience, our subtransmission system (115 kV) is looped while our distribution system (34.5 kV or 13.8 kV) is radial with N.O. connection from other source for load shifting in case of troubles. Back there, one of our basic criteria is to plan for expansion when the distribution line reaches approx. 70% loading. Expansion could either be by upgrading the involve feeder or expansion from another source which can unload the affected feeder through load shifting. We evaluate base on actual peak loading and not based on applied connected loads being serve by the feeders.
Currently, I am working for an electric utility away from my country but which is having different system and somehow different philosophy. Here, we have a system which is independent having our own generation and T&D system. We have inter-tie with a larger network/system @ 380kV. However, from 115 kV system dowstream, all are radial but with redundancy. Community areas are serve by 13.8 kV loop (2-feeders with N.O. connection in between for redundancy). For connecting new or additional loads, I would evaluate the feeder based on actual historical peak load of the loop to check if capacity is still available for the new connection. Of course with due consideration of the possible future load increase based on the connected load. Ideally, I would recommend favorably if peak load has not reached 80%-85% and the potential for increase is still there due to the connected transformer capacities.
However, operations people will always argue and sometimes reject recommendation saying that the same feeder is over committed considering the connected load (despite peak loading way below the capacity of the single feeder). I know that their consideration is mostly on technical side and somehow not considering the economic side of this philosophy.
We are planning to propose to adapt an official philosophy which considers the peak load as a means to evaluate utilization of facilities (not only feeders but also dist. XF).
In this regard, I am bench marking to gather prevailing philosophy on this issue. We would appreciate if somebody can inform of their followed philosophy in their utility planning or if there are other utility company following the committed load/connected load instead of the peak load in their planning criteria?
Thanks!
CK