Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Subtask Length

Status
Not open for further replies.

Irishkid

Computer
Jun 15, 2008
2
hello,

I have the following problem. I am trying to create a project plan that will show the following.

I have a Main Task that should last 4 months. So starts September 1st and finished December 31st. This task has 3 sub tasks which will take place during those 4 months, however the length my work in the subtasks is as follows:

Task1 lasts 20 days
Task2 lasts 10 days
Task3 lasts 10 days.

For the life of me I cannot get the main task to show 4 months and then the subtasks to show 20,10 and 10? Has anyone any idea how this can be displayed in MS Project?

Thanks
 
Replies continue below

Recommended for you

Are you refering to a Summary Task? You simply indent the subtasks under it.

TTFN

FAQ731-376
 
and connect the subtasks together using the predessor column with a Finish to Start relationship.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor