I infrequently analyze/design anchored sheet pile retaining walls with sloped dredge lines in front of the retaining wall. Based on the “recommendations” of senior engineers within the company, a wall is idealized with a horizontal dredge line. The determination of the horizontal dredge line is that elevation that provides a bench in front of the retaining wall that is approximately equal to the height of wall (top of wall to top of dredge line at wall interface.)
Is it proper or within the limits of the Coulomb’s passive earth pressure equation to enter a negative value for an inclined backfill (slope downward from the horizontal) and get a “valid” Kp value? All texts that I’ve seen use the equation with a positive backfill angle (slope upward from the horizontal.) Does anyone have a solid reference that discusses this specific use of Coulomb’s eq. so that I can use as a point of discussion with the senior engineers?
Maybe this is the best way to look at a retaining wall with a sloped dredge line? What do others do?
Thanks - VQ
Is it proper or within the limits of the Coulomb’s passive earth pressure equation to enter a negative value for an inclined backfill (slope downward from the horizontal) and get a “valid” Kp value? All texts that I’ve seen use the equation with a positive backfill angle (slope upward from the horizontal.) Does anyone have a solid reference that discusses this specific use of Coulomb’s eq. so that I can use as a point of discussion with the senior engineers?
Maybe this is the best way to look at a retaining wall with a sloped dredge line? What do others do?
Thanks - VQ