-
1
- #1
Robert216
Structural
- Apr 11, 2007
- 35
Here is the big question: In a multi-story reinforced concrete building, do shores need to be released and "snugged up" before shoring levels above? This is what makes sense to me. This allows the beams to deflect and "carry their on load".
Let's begin with what most of us agree on. Starting from the ground, and assuming that all beams in the bay are the same section, the lowest level will most always be the stiffest (ie: ground is stiffer than 2nd floor beam, 2nd floor beam will be stiffer than 3rd, etc) , based on age of concrete.
Now lets get into the "gray area". Let's look at a scenario where shores are never released. Lets say 2nd, 3rd, and 4th floors are shored and placed (never released) and then shores were removed from beneath the 2nd floor.It seems that before the shores were removed between the ground and the 2nd floor, all of the load would travel through the shores (beams would be unable to deflect, therefore would be unable to have a moment, therefore would be unable to carry a load. My first thought is that this would cause post shores to be overloaded (assuming that the post shores were not designed to carry 3 levels of elevated structure). Now my thought is since the 2nd level is at the bottom, unshored, and stiffest (relatve to the above), it will now carry three floors of load. Have I missed something here? Did we not learn in school that if there is not deflection, a beam cannot work? How in the world can a beam carry a load if it cannot deflect? Some insight on this would be greatly appreciated. It seems like some engineers swear up and down that re-shoring is not neccessary, while others swear up and down that it is. If anyone knows of any reliable sources that are available or even if there are any articles documenting failures or problems caused by one or the other, that would be very helpful as well. Thanks, Rob.
Let's begin with what most of us agree on. Starting from the ground, and assuming that all beams in the bay are the same section, the lowest level will most always be the stiffest (ie: ground is stiffer than 2nd floor beam, 2nd floor beam will be stiffer than 3rd, etc) , based on age of concrete.
Now lets get into the "gray area". Let's look at a scenario where shores are never released. Lets say 2nd, 3rd, and 4th floors are shored and placed (never released) and then shores were removed from beneath the 2nd floor.It seems that before the shores were removed between the ground and the 2nd floor, all of the load would travel through the shores (beams would be unable to deflect, therefore would be unable to have a moment, therefore would be unable to carry a load. My first thought is that this would cause post shores to be overloaded (assuming that the post shores were not designed to carry 3 levels of elevated structure). Now my thought is since the 2nd level is at the bottom, unshored, and stiffest (relatve to the above), it will now carry three floors of load. Have I missed something here? Did we not learn in school that if there is not deflection, a beam cannot work? How in the world can a beam carry a load if it cannot deflect? Some insight on this would be greatly appreciated. It seems like some engineers swear up and down that re-shoring is not neccessary, while others swear up and down that it is. If anyone knows of any reliable sources that are available or even if there are any articles documenting failures or problems caused by one or the other, that would be very helpful as well. Thanks, Rob.