mdrewelow
Civil/Environmental
- Aug 5, 2004
- 1
We have a site that needs to be manned by 2 man shifts 24 hours per day. Does anyone out there have suggestions as to how to arrange the shifts. Our best solution is 4 teams of 2 men on a team. Teams A B C D. Team A and B do 12 hour shifts Sun, Mon and Tues. Wed all 4 teams do 6 hour shifts. Team C and D do 12 hour shifts on Thur, Fri and Sat. This works out to 42 hours a week per man. Ideas please!!!