Rasheed Khan
Mechanical
- Aug 22, 2016
- 10
As per the API-660(2007) Para 10.3.9 states that " Flanged joints that have been taken apart after a hydrostatic test shall be reassembled with unused
gaskets and re-hydrotested". The question is, do we need to have second hydro test at site even the first hydro test at shop have been completed?
gaskets and re-hydrotested". The question is, do we need to have second hydro test at site even the first hydro test at shop have been completed?