lumbee
Mechanical
- Feb 26, 2003
- 15
I am designing a foundation for a metal building that is being built over a partial existing slab. I am able to use hairpins at all columns except two. These two locations are near the existing slab and prevent me from using hairpins. Does anyone have a suggestion on how to handle the 9 kip thrust load? Has anyone used a shear block at the bottom of a footing before to handle the thrust loads? If so, what is the procedure for getting the depth and with of the shear block?
Lumbee
Lumbee