Dennis1234
Computer
- Apr 25, 2006
- 2
I am trying to use Actual Work and Remaining Work to adjust the planned Finish date of a task in progress (with an Actual Start date) when resource leveling. However, when I level, project seems to set the planned Finish date based on the Remaining Work from the Actual Start date rather than from the current/status date. In other words, Project seems to assume that the Remaining Work is as of the Actual Start date rather than as of the status/current date.
I thought Remaining Work calculations were based on the status (by default current) date. Is there a setting I need to adjust so that it works that way, or am I going about this incorrectly?
Thanks in advance for your help.