Hello,
Concrete high rise has reshoring jacks used for reshoring slabs. Jack capacity is specified with a safety factor of 3:1. I am designing using LRFD, so I am comparing SLS slab load above to the working jack capacity and the ULS slab load to the 3x(Working Jack Capacity)?