RAgrawal
Electrical
- Aug 31, 2001
- 59
We are having a large industrial load with about 500 MW internal generation. Our plant normally operates in parallel with Grid. In recent past, there had been severe frequency fluctuation in the Grid, which resulted into tripping of some of our internal Generators because of delayed islanding (at present islanding is given on pure Under frequency or pure Over frequency, dir O/C, Dir E/F, reverse power). I want to install df / dt protection for islanding.
For this i need to know how to arrive at setting of df /dt. I will appreciate, if you can provide guidelines / standards / technical papers about the same.
For this i need to know how to arrive at setting of df /dt. I will appreciate, if you can provide guidelines / standards / technical papers about the same.