3doorsdwn
Structural
- May 9, 2007
- 162
I've got a structure I'm designing that will be in place about 4 months (only for 4 months). The thing I'm trying to decide is whether or not to use full lateral loads or something less. I know ASCE puts out a standard on this [i.e. ASCE 37]....my question is (for anyone who has this standard): does this standard address load magnitude vs. specific duration time? And (if this is addressed and you feel generous): what kind of magnitude are we talking for 4 months duration (approximately)?