schuman
Computer
- Nov 28, 2007
- 1
Newbie
I'm trying to figure out how to accomidate this setup
Main Task
MainSubTask A
SubTask2
SubTask3
MainSubTask A
SubTask1
This is repeated many many time.
The way we operate is the MainSubTask could span 3 months
The Subtasks may have an estimated work time of 10 hours
The Actual work to complete the task may only end up being 5 hours.
How to I set Project 2003 to maintain the est. 10hrs (budget) and show the task as complete at 5 hours.
Currently if I set the task to 100% complete the actual hrs switches to 10hrs. I want to show completed in 5, budgeted 10, and the task is complete.
Thanks
I'm trying to figure out how to accomidate this setup
Main Task
MainSubTask A
SubTask2
SubTask3
MainSubTask A
SubTask1
This is repeated many many time.
The way we operate is the MainSubTask could span 3 months
The Subtasks may have an estimated work time of 10 hours
The Actual work to complete the task may only end up being 5 hours.
How to I set Project 2003 to maintain the est. 10hrs (budget) and show the task as complete at 5 hours.
Currently if I set the task to 100% complete the actual hrs switches to 10hrs. I want to show completed in 5, budgeted 10, and the task is complete.
Thanks