I have an existing 42" diameter prestressed concrete cylinder pipe (pccp)for a water transmission main. Per original design calculations, the minimum and maximum allowable load over the pipe is 4 feet and 11 feet respectively. Currently, the pipe is within this allowable 'cover zone'.
However, new grading design would exceed 11 feet of cover over the pipe. Is there a design criteria and/or method that I can use in order to exceed this maximum cover? Someone has suggested a cradle or soil arch over the pipe, but I cannot find any literature on it.
Thanks
However, new grading design would exceed 11 feet of cover over the pipe. Is there a design criteria and/or method that I can use in order to exceed this maximum cover? Someone has suggested a cradle or soil arch over the pipe, but I cannot find any literature on it.