zayed78
Petroleum
- Nov 23, 2004
- 16
Gents,
I have segments of ~ 50 m Non-Piggable Pipe at well site ass you this section we can to run pig through it for cleaning or chemical treatment. Due to our situation we forced to suspended all our production wells and we applied the massive suspension / Mothballing for main flow line and individual flow lines by using pigging with corrosion inhibit /biocide batch treatment then blown and dry, However we faced problem regarding a well site piping as you know the such piping experienced corrosion due to deposit of scale inside it which cause corrosion so I need you advise about the optimum suspension method for such case??
Note that suspension period could be reaches 3 years or more fluid inside the pipe crude oil with water (water cut could be 50 % to 95%)
Zayed
I have segments of ~ 50 m Non-Piggable Pipe at well site ass you this section we can to run pig through it for cleaning or chemical treatment. Due to our situation we forced to suspended all our production wells and we applied the massive suspension / Mothballing for main flow line and individual flow lines by using pigging with corrosion inhibit /biocide batch treatment then blown and dry, However we faced problem regarding a well site piping as you know the such piping experienced corrosion due to deposit of scale inside it which cause corrosion so I need you advise about the optimum suspension method for such case??
Note that suspension period could be reaches 3 years or more fluid inside the pipe crude oil with water (water cut could be 50 % to 95%)
Zayed