mmfranke
Computer
- Dec 10, 2008
- 7
Hello again
In addition to accounting for the actual time and resources needed to hold a large extended meeting (see previous thread entitled "Meeting Overhead"), I'd like to add a task for "meeting preparation" ahead of the meeting (prep ends when the meeting starts), and "meeting follow-up" that starts immediately after the meeting is complete.
Furthermore, the target date for the meeting is a milestone that I'd like to be able to move around as departmental priorities change, and I'd like the prep, meet, and follow-up tasks to move around accordingly.
Finally, the meeting milestone task is in a different project file as the others. I know how to do cross-project links, but I wonder if there are easier ways to deal with the lengthy cross-project "URLS" than I know of, especially if we're talking about using atypical linkages -- like Start-to-Finish or something.
Sorry for being so verbose. How do I link these tasks to make this happen?
Thanks.
Mike
In addition to accounting for the actual time and resources needed to hold a large extended meeting (see previous thread entitled "Meeting Overhead"), I'd like to add a task for "meeting preparation" ahead of the meeting (prep ends when the meeting starts), and "meeting follow-up" that starts immediately after the meeting is complete.
Furthermore, the target date for the meeting is a milestone that I'd like to be able to move around as departmental priorities change, and I'd like the prep, meet, and follow-up tasks to move around accordingly.
Finally, the meeting milestone task is in a different project file as the others. I know how to do cross-project links, but I wonder if there are easier ways to deal with the lengthy cross-project "URLS" than I know of, especially if we're talking about using atypical linkages -- like Start-to-Finish or something.
Sorry for being so verbose. How do I link these tasks to make this happen?
Thanks.
Mike