Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Meeting Overhead

Status
Not open for further replies.

mmfranke

Computer
Dec 10, 2008
7
Hello. I'd like to account for the overhead of formal design review meetings in terms of resource usage and cost accounting. Say my meeting will be two four-hour sessions, over two days.

What I've done to try and account for this is to enter the task as a fixed duration of two days, non-effort-driven, and then tried entering the resources that will be involved, each at 50% usage. What I'm seeing is different values for their respective costs (in the "Task Information" dialog), even though their rates are all identical. The only thing I can think of that's different between the resources that seems to correspond to the different cost calculations is that they don't all have the same "maximum units." But why would max units enter into the cost calculation?

I've attached a picture of my Task Info dialog.

Help... Thanks in advance....
 
Replies continue below

Recommended for you

If you look at the resource usage page, you should be able to see the actual hours incurred by each resource and verify that you're getting what you think you should be getting.

TTFN

FAQ731-376
 
Thanks! The Resource Usage page indeed showed different numbers of hours for the different resources. I manually edited them in the Resource Usage page, and Voila!

But WHY? If I have a fixed-duration, non-effort-driven task that's two days long, I would think that assigning any resource to the task at 50% would result in 8 hours of charged time (assuming a normal 8-hour work day, of course).

What am I missing?

Mike
 
MSP almost always has had some funky issues with fractional resources, and this might be another one of them. There may have been some anomaly in the way, or order, in which you entered the data.

TTFN

FAQ731-376
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor