I have used Microsoft Project on and off for some time. I would still say I am something of a novice with all its options, but am learning as I go on.
In the past in a different office I have just put in the main details and linked them up through the predecessors. Whilst doing this a duration period of 5 days would relate to a working week and extend for example from a start date of Friday 10th July to Friday 17th July. That way weeks were easy to insert as a multiple of 5 days.
Now when I put in the 5 days duration I am often getting Friday 10th July to Monday 20th July. Which is the right way to show 5 working days duration?
Added to this some of the entries vary even further with a 5 day duration relating to say a 4 day period. I presume its not a bug in the programme and something to do with the settings, but having checked other computers in the office I don't seem to be the only one having difficulties.
Has anyone else had similar problems?
Any assistance you can offer would be appreciated and happy to try to answer any questions.
Thanks in advance.
In the past in a different office I have just put in the main details and linked them up through the predecessors. Whilst doing this a duration period of 5 days would relate to a working week and extend for example from a start date of Friday 10th July to Friday 17th July. That way weeks were easy to insert as a multiple of 5 days.
Now when I put in the 5 days duration I am often getting Friday 10th July to Monday 20th July. Which is the right way to show 5 working days duration?
Added to this some of the entries vary even further with a 5 day duration relating to say a 4 day period. I presume its not a bug in the programme and something to do with the settings, but having checked other computers in the office I don't seem to be the only one having difficulties.
Has anyone else had similar problems?
Any assistance you can offer would be appreciated and happy to try to answer any questions.
Thanks in advance.