I'm managing a lot of small projects on a small team, sometimes having the need to have a global view of my team allocation.
I thought MSP could help me on the task of controlling overallocation, but I met a couple of unexpected problems...
For me, the most serious is the following:
I have 3 .mpp files: a master project - MP - where all my resources are defined, and 2 project files - P1 and P2 - where i define sets of tasks to be performed by my resources.
Once the tasks are defined in P1, I make it us the MP resource pool, assign the resources to it, and level the resources, so that each one does not have more than 8 h/day.
Then I save P1 and MP. Now I open P2, make it made use of the MP resource pool too, assign the resources to tasks, and now is where my problem begins....
If I try to level the resources, even specifying to preserve the existing allocation, it does not respect the times already allocated for P1, and re-establishes new dates for it!!!
All I wanted is that the existing allocation load and already assigned dates were taken into account; instead of that, the allocation is preserved but most of the times the project dates are also moved.....
Does anyone knows if there is a way of accomplish this?
Thanks in advance
jmn
I'm managing a lot of small projects on a small team, sometimes having the need to have a global view of my team allocation.
I thought MSP could help me on the task of controlling overallocation, but I met a couple of unexpected problems...
For me, the most serious is the following:
I have 3 .mpp files: a master project - MP - where all my resources are defined, and 2 project files - P1 and P2 - where i define sets of tasks to be performed by my resources.
Once the tasks are defined in P1, I make it us the MP resource pool, assign the resources to it, and level the resources, so that each one does not have more than 8 h/day.
Then I save P1 and MP. Now I open P2, make it made use of the MP resource pool too, assign the resources to tasks, and now is where my problem begins....
If I try to level the resources, even specifying to preserve the existing allocation, it does not respect the times already allocated for P1, and re-establishes new dates for it!!!
All I wanted is that the existing allocation load and already assigned dates were taken into account; instead of that, the allocation is preserved but most of the times the project dates are also moved.....
Does anyone knows if there is a way of accomplish this?
Thanks in advance