DrThink
Structural
- Mar 19, 2004
- 9
I have a 150 kip 11 feet diam. tank that I am doing a foundation for. There are basements of an existing buildings directly adjacent to the tank. I was thinking of pouring a 10' deep x 12'X12' concrete blob in the ground to ensure no lateral pressure against the basement walls.
I was planning on using lean concrete.
My question is:
Do I have to worry about heat of hydration for this much concrete? What lift htg is acceptable and how much time between lifts?
I was planning on using type IIA concrete. Not too concerned if there is minor cracking.
Thanks
I was planning on using lean concrete.
My question is:
Do I have to worry about heat of hydration for this much concrete? What lift htg is acceptable and how much time between lifts?
I was planning on using type IIA concrete. Not too concerned if there is minor cracking.
Thanks