LesserKey
Civil/Environmental
- May 9, 2010
- 4
Helping out a non-profit organization that runs a local railway. They suffered what looks like a slide slope failure with an approximate amount of soil to be moved at around 250,000 cy to 500,000 cy.
There is large trees mixed into the soil and am wondering of any ideas on inexpensive ways to clean this up without damaging the tracks. The site is pretty remote and hauling out the material would be by rail. Any help or ideas would be greatly appreciated.
Thanks in advance.
Pictures that might be helpful.
- The slide over the tracks. Looking at the photo, the slope to the left (failure slope)is roughly 50% and the slope to the right is roughly 50%.
There is large trees mixed into the soil and am wondering of any ideas on inexpensive ways to clean this up without damaging the tracks. The site is pretty remote and hauling out the material would be by rail. Any help or ideas would be greatly appreciated.
Thanks in advance.
Pictures that might be helpful.
- The slide over the tracks. Looking at the photo, the slope to the left (failure slope)is roughly 50% and the slope to the right is roughly 50%.