sager880
Chemical
- Jun 13, 2016
- 3
Hi, i'm facing some difficulties on how to proceed and hope someone can extend their help. PSV was manufactured with maximum operating pressure 7 barg and during construction the PSV is unable to be located at less or equal 7 meters of hight(10%) and the only possibility is to relocate it to 17 meters hight. therefore, the operating pressure will certainly be effected due to new hydraulic calculation and the new maximum operating pressure will change to around 5.3 barg.
i'm not sure wether this will effect the basis of design for the PSV, i understand this will take longer time before PSV activate i.e. around 1 barg. also, this PSV is located downstream of HE and designed for external fire.
so my question: 1) is it possible to still use the same PSV on the new location even though operating pressure will is reduced. also, the set point won't be changed (MAWP of all equipment considered i.e. higher than set point.
2) to understand the situation how does the operating pressure effecting design of PSV (if applicable seat, size, flow or not related?)
the density of the fluid is 940Kg/m3
thanks and regards,
i'm not sure wether this will effect the basis of design for the PSV, i understand this will take longer time before PSV activate i.e. around 1 barg. also, this PSV is located downstream of HE and designed for external fire.
so my question: 1) is it possible to still use the same PSV on the new location even though operating pressure will is reduced. also, the set point won't be changed (MAWP of all equipment considered i.e. higher than set point.
2) to understand the situation how does the operating pressure effecting design of PSV (if applicable seat, size, flow or not related?)
the density of the fluid is 940Kg/m3
thanks and regards,