Could somebody kindly advise me :
During hydrostatic test of water pipeline, the pipeline is filled up with water under the testing pressure of 16 bar(working pressure 10 bar).How long should this pressure sustained? The client is asking for holding the pressure for 10 hours. Is it possible to hold this? The pipeline is of socket-spigot joints and some flanged joints.
I saw some reference saying that is is about 10 to 20 min. Is it true?
Thanks!
During hydrostatic test of water pipeline, the pipeline is filled up with water under the testing pressure of 16 bar(working pressure 10 bar).How long should this pressure sustained? The client is asking for holding the pressure for 10 hours. Is it possible to hold this? The pipeline is of socket-spigot joints and some flanged joints.
I saw some reference saying that is is about 10 to 20 min. Is it true?