SubcontractorPolice
Civil/Environmental
- Aug 30, 2014
- 1
So these subcontractors pour a 24" wide by 10" deep shallow foundation with 3,000 psi concrete covering only horizontal steel. This is the perimeter foundation for a future stem wall. 30 minutes later they stab in the vertical steel into wet concrete and make feeble attempt to hook under the covered horizontal steel.
Then these jokers come back not 15 hours later and construct a CMU masonry block stem wall four blocks high over half the foundation and call it quits. They'll come back to finish the perimeter stem wall foundation tomorrow.
So at best you'll have 15 hours of cure over half the concrete and 30 hours over the other half. The concrete is not high early strength. No cylinders pulled, nothing. They'll probably bring fill the next day and bring it level with top block minus 4" then pour the slab the next day.
What is going to happen to the concrete that's been completely loaded, stem wall, slab and all not even 5 days from first pour? You have to be completely incompetent to allow this kind of practice.
Ranting in Savannah Georgia.......
Then these jokers come back not 15 hours later and construct a CMU masonry block stem wall four blocks high over half the foundation and call it quits. They'll come back to finish the perimeter stem wall foundation tomorrow.
So at best you'll have 15 hours of cure over half the concrete and 30 hours over the other half. The concrete is not high early strength. No cylinders pulled, nothing. They'll probably bring fill the next day and bring it level with top block minus 4" then pour the slab the next day.
What is going to happen to the concrete that's been completely loaded, stem wall, slab and all not even 5 days from first pour? You have to be completely incompetent to allow this kind of practice.
Ranting in Savannah Georgia.......