I am dealing with a pumping system for the transportation of 30 m3/day.There is another stream with 1 % suspended solids .That stream is 150 m3/day.Total is 180m3/day
MY enquiry is
1-On what baiss I will calculate head losses ie taking clean water into account or sewerage water...
2-the fluid has to be transported to 1.2 km
3-There is no height involved during transportation
like the pipe will be at the ground level through out
so on what basis I will calculate friction losses
I am thinking to use a 4 inch poly pipe
Thanks
MY enquiry is
1-On what baiss I will calculate head losses ie taking clean water into account or sewerage water...
2-the fluid has to be transported to 1.2 km
3-There is no height involved during transportation
like the pipe will be at the ground level through out
so on what basis I will calculate friction losses