sfat
Structural
- Sep 8, 2008
- 39
Formwork design is the responsibility of Contractor, and structural consultant should not be asked to check and approve it, rather a third party should do it.
I would like to know what is the general practice for Formwork design review and approval (submitted by Contractor) in other countries. Does any Structural Consultant, if asked, accept and do that as additional scope? I am talking about normal shearwall/column and floor slab formwork (not special case as transfer girder or slab).
Please comment as per your experience and practice. Thanks.
I would like to know what is the general practice for Formwork design review and approval (submitted by Contractor) in other countries. Does any Structural Consultant, if asked, accept and do that as additional scope? I am talking about normal shearwall/column and floor slab formwork (not special case as transfer girder or slab).
Please comment as per your experience and practice. Thanks.