I am using Project 2007, and note I can add Indicators to custom feilds.
Can anyone tell me the formulae I need to enter so I can show the following:
1. start date is greater than status date (not yet reached)
2. start date is equal to or less than status date (can/should commence)
3. work complete behind scheudle
4. work complete is on track
5. work has not started but should have started
Thanks,