I have 5 vertical fire sprinkler risers on the reduced pressure side of a PRV. FDC, Fire pump and standpipe are on the other side of the PRV. AHJ wants the FDC to split and supply both sides of the PRV. This does not make sense to me, is there a code requirement for this. I will strategically place check valves to accomplish this, but does anyone know why the FDC needs to be physically connected to both side of the PRV? Thanks - J