SeanSweeney
Civil/Environmental
- Mar 16, 2005
- 173
When I write in a duration of 5 days I get dates from monday to monday next week. That's fine. When I do the same for 10 days I get to tuesday the following week and so on to wednesday for 15 days. Same applies if I use 1 week or 2 weeks.
There are no extra free days in between, using a standard calendar. I am using a norwegian version (Project 2003).
Why is this happening. I thought a week was 5 days (working).
Cheers. Sean.
There are no extra free days in between, using a standard calendar. I am using a norwegian version (Project 2003).
Why is this happening. I thought a week was 5 days (working).
Cheers. Sean.