Hello everybody, and I hope someone can knock some of the rust off my brain regarding the NEC...
I recently inherited a 1500 kVA stepdown transformer, 4.16kV Delta to 480 V Delta that feeds a couple of motor control centers in an industrial plant. There are no grounding transformers on the secondary system, thereby making this an ungrounded 480 v system. In light of this, my questions is:
Is a ground fault detection system (e.g. "three-light system" or something similar), required by the NEC for this installation to alert the plant operator of a ground fault, should one occur. Right now there is no ground fault indication system installed. If it is an NEC requirement, can someone cite the particular reference in the NEC?
Thanks for your help.
I recently inherited a 1500 kVA stepdown transformer, 4.16kV Delta to 480 V Delta that feeds a couple of motor control centers in an industrial plant. There are no grounding transformers on the secondary system, thereby making this an ungrounded 480 v system. In light of this, my questions is:
Is a ground fault detection system (e.g. "three-light system" or something similar), required by the NEC for this installation to alert the plant operator of a ground fault, should one occur. Right now there is no ground fault indication system installed. If it is an NEC requirement, can someone cite the particular reference in the NEC?
Thanks for your help.