I am double checking what the standard practice is for determining the unsupported length of a concrete column on the first storey of a building (without getting in to anything like horizontal soil springs, etc) .
I have a situation where my footing was lowered about 9' below the slab on grade to accommodate some piping. Is the unsupported length from:
A) the underside of the slab to the top of the footing
or
B) the underside of Level 2 slab to the slab-on-grade. The slab-on-grade is 5" thick with mesh and the soil is properly compacted.