BSQUAREDBUCKEYE
Mechanical
- Sep 15, 2005
- 35
As a supplier I am conflicted between a FM inspector that says the piping from the 300# flanged steam drum outlet of the high pressure boiler to the flanged non-return valve, the flanged non-return valve, the flanged piping between the flanged non-return valve and the first flanged stop valve, the drain valve piping, the drain valve and first flanged stop valve all have to be supplied with Certified Material Test Reports and documented on an ASME data report Form P-1 and installed by an ASME "S", "A", or "PP" stamp holder and the form signed and stamped by the stamp holder's commissioned Authorized Inspector.
And the valve manufacturers I represent that say only the non-return valve, the piping from it to the boiler drum, and the piping from the non-return valve to the first stop valve needs to be documented and stamped.
I do not have a problem providing the CMTRs, or stamped pipe spools and non-return valve, but the stamping of the first stop valve and drain valve is a problem for the manufacturers.
Can someone clarify this?
And the valve manufacturers I represent that say only the non-return valve, the piping from it to the boiler drum, and the piping from the non-return valve to the first stop valve needs to be documented and stamped.
I do not have a problem providing the CMTRs, or stamped pipe spools and non-return valve, but the stamping of the first stop valve and drain valve is a problem for the manufacturers.
Can someone clarify this?