Mining
Jun 24, 2011
3
I have set up a project and it is using a calander I have defined as 7 days per week, but the tasks are avoiding being worked/allocated on Sat/Sun in Gantt view. Why is my project not following my 7 days a week rule?

Cheers.
 
Replies continue below

Recommended for you

Dear Prymemover,is possible that all resources are working on a different calendar (resources sheet/calendar)