We have a 24940GRDY system, (14.4kV L-G) and in order to avoid installing a MV single phase metering unit to feed a small 37.5kVA single phaseload requiring 2400V, we plan to use some units we have in stock, ie a step down 100kVA 14,4kV-120/240, and connect its 240V to the 240V LV of a 75kVA 2400-120/240V. We would insert a standard single phase LV metering unit at the connection point between the 2 LV .