ChevyBuilder
Mechanical
- Jun 2, 2003
- 5
I'm looking to add an 45 x 20 paito slab to the rear of my house and garage. The former farm land, slightly clay soil is frozen for months at a time here in upstate New York. The Back yard grade is flat, Front yard starts to slope down, 10-15 feet from the front of the structure. There are 3 roof gutters that serve 1500sqft, one at each end of the slab and one in the middle, they will need to be extended beyond the slab. The slab pitch will put another 900sqft of runoff at the slab edge. A contractor suggested a french drain or drywell. In my research so far I have seen these used to move water from soil through fabric, stones, and sand into pipes then to an acceptable location. My application calls for moving water the other way...into the ground.
I want this patio to aid in drainage, what would be suggested?
Building Automation Professional
I want this patio to aid in drainage, what would be suggested?
Building Automation Professional