Hello all:
I am putting a new 4160V diesel genset in service on an existing med voltage transfer switch. To verify phase rotation I have a 25kV meter with two probes. I plan on reading utility A to gen A and so on with B and C, watching them go to zero volts as they drift in and out. If all three drift to zero I have the right rotation...accurate??
I am putting a new 4160V diesel genset in service on an existing med voltage transfer switch. To verify phase rotation I have a 25kV meter with two probes. I plan on reading utility A to gen A and so on with B and C, watching them go to zero volts as they drift in and out. If all three drift to zero I have the right rotation...accurate??