I have an AC overlay project for an old Park parking lot.
I checked as-built plans and found that the depth of the existing AC is only 2.5" deep.
It gives me a concern that 1.5" deep grinding would "BREAK" the existing AC so it might cause repeating the same job in the near future.
The owner mentioned that they have a limited fund available only for overlay works rather than replacing whole pavement. The size of the parking is a little over 1 acre.
What would be an optimum solution for this type of AC overlay job that a good civil engineer can advise?
Any information or advise would be highly appreciated.
Have a wonderful day.
I checked as-built plans and found that the depth of the existing AC is only 2.5" deep.
It gives me a concern that 1.5" deep grinding would "BREAK" the existing AC so it might cause repeating the same job in the near future.
The owner mentioned that they have a limited fund available only for overlay works rather than replacing whole pavement. The size of the parking is a little over 1 acre.
What would be an optimum solution for this type of AC overlay job that a good civil engineer can advise?
Any information or advise would be highly appreciated.
Have a wonderful day.