buzzp
Electrical
- Nov 21, 2001
- 2,032
I am in the US and have an ONAF transformer rated for 20MVA with a 100kV delta primary and 21.6kV Y secondary. The %Z is 6.03% at 100k-21.6k.
The X/R is unavailable.
If I remember correctly, the X/R ratio I can safely use for a transformer this big is 20 when determining my maximum fault current. The software I use, uses X/R and not Z. I want to check my hand calculations, using %Z, with what the software tells me (using X/R).
The X/R is unavailable.
If I remember correctly, the X/R ratio I can safely use for a transformer this big is 20 when determining my maximum fault current. The software I use, uses X/R and not Z. I want to check my hand calculations, using %Z, with what the software tells me (using X/R).