dirtsqueezer
Geotechnical
- Jan 29, 2002
- 269
I saw a project today where the contractor was backfilling his 6-8' steam line trench with wet sand out of the back of a concrete truck! I walked over it after it was filled- not compacted. The sand was well graded, saturated, and less than 2000pcf (yielded to foot pressure). My question is, with that much of a profile, won't this trench settle over time? Even with the 'jetting' effect? All areas are for existing city streets.