I work on a piping system, designed according to ASME B31.3, and I want to install a welded thermowell on a run pipe.
Do you know what is required by the B31.3 code for the design in this case?
Is there a specific chapter to use, or can I calculate the connection like a "branch connection"?
Thank you
F67
I work on a piping system, designed according to ASME B31.3, and I want to install a welded thermowell on a run pipe.
Do you know what is required by the B31.3 code for the design in this case?
Is there a specific chapter to use, or can I calculate the connection like a "branch connection"?