Weirdness in Resource Usage View

Status
Not open for further replies.

NCCaryME

Mechanical
Aug 1, 2003
59
I have a series of tasks that are linked. In the Gantt Chart view, I can clearly see the series of tasks starting a certain day, and the following tasks happening consecutively like I would suspect.

Now, the weird part: When I go to my Resource Usage view, I see one of my resources working on item #3 in the list currently, and full-time. Items 1 and 2 in the series have not occured yet, and this resource is assigned to all 3. I go back to my Gantt Chart, and everything is fine. The two views are contradicting each other, and the Resource Usage view is ignoring the links I set between the tasks.

Any ideas what might be going on here?

 